18/01/2010 – DAY 28

Plot 1 Staircase WellIMG00607-20100118-1157 

Lounge to Dining RoomIMG00608-20100118-1204 

Plot 1 from Plot 2IMG00610-20100118-1208 

Plot 1 from the Corner of Plot 2IMG00611-20100118-1209 

Plot 1IMG00612-20100118-1210

15/01/2010

Due to the big freeze and regular snowfall over the past few weeks the site had to be closed for a while as works were not able to commence due to the weather conditions.

Wednesday, 16 December 2009

14/12/2009 - DAY 27

Goodby Rd walls flying up


Goodby Rd window openings


Goodby Rd flue blocks for the fireplace


Goodby Rd entrance door

Wednesday, 9 December 2009

09/12/2009 - DAY 22

Goodby rd plot 1 brick detail


Goodby rd footprint plot 2


Goodby rd beam and block


Goodby rd garage footprint plot 2